Reinstatement and Modification of Portable Accommodation Modules for Sea Trucks Group

Reinstatement and Modification of Portable Accommodation Modules for Sea Trucks Group

In November 2016, Sea Trucks Group (STG) awarded Specialist Services the contract for the reinstatement and modification of the Accommodation Modules built for STG in 2014, to form a block 11 modules wide and 4 modules high.

Project: Reinstatement and Modification of Portable Accommodation Modules
Client: Sea Trucks Group
End User: INPEX
Location: Australian waters, 890km West of Darwin
Project Completion: 15th May 2017

Project requirements

Sea Trucks Group required reinstatement and modification works on the Accommodation Modules that Specialist Services manufactured and delivered to them in 2014. We have been awarded this reinstatement and modification job based on the excellent work we did on the 2014 project with a fast track execution, including a production schedule of all 48 modules reduced to 16 weeks. The new Accommodation Block was required to be modified in order to provide Accommodation, Locker Room, Washroom, Toilet, Office, Recreation and Conference facilities, accommodating up to 224 personnel on board. The modules were required to be connected to form a block 11 modules wide and 4 modules high.

Within the requirement, the existing Mess Room needed to be converted to a Gymnasium, and the Locker Room and Dry Store to be converted into Recreation Rooms. STG also required communication system upgrades, HVAC improvements, door and panel modifications, installation review and supply of required consumables for the new stacking arrangement, and supply of all materials required to complete the upgrade. Electrical engineering / drawing updates and a module stacking study were also required by STG for this project.

Solution

The project execution by Specialist Services has been carried out in line with STG requirements at the site in Batam, converting the Mess Room into a Gymnasium, and the Locker Room and Dry Store into Recreation Rooms, as per the drawings provided by the client.

Specialist Services team also completed the A/C drainage system upgrade, electrical and Fire & Gas interconnection cabling works, the provision of an Electrical Distribution Panel for each floor, as well as the upgrade of the communication system, which included the relocation of patch panels from outside the module into its interior and mounting required infrastructure to allow the installation of existing switches within the modules.

A total of 44 modules were installed on the Barge, connecting the modules to each other in rows of 11 modules with 4 stacking. The resulting Accommodation Facility was built in compliance with ABS guides for Portable Accommodation Modules and MLC (Maritime Labour Convention 2013).

Conclusion

In line with the project requirements, we provided a highly skilled team of specialists from our Dubai facility to manage the project and carry out the reinstatement and modification works at the client’s venue of choice, a shipyard in Batam, Indonesia.

The project was successfully completed by Specialist Services within the specified timeframe. At the end of the project were issued as built drawings incorporating all the modification works, and Specialist Services supported STG with the documentation requirements for obtaining an updated ABS certification.

The high quality modifications, upgrades and reinstatement works provided by Specialist Services resulted in comfortable living and working environments. All works have been completed to a very high standard and STG Management was very satisfied with Specialist Services’ team performance.